Fortec was engaged by Singleton Council to do the bridge abutment repair works at Herbert Street Bridge, Christian Badior Bridge and Maryvale Bridge as a part of the Council’s infrastructure renewal program. The project involved to construct a
solution to repair the existing damages to the abutments and scour protection of 3 bridges by providing enhanced durability, increased load-bearing performance, and reduced long-term maintenance requirements.
Singleton Bridges Abutment Repairs
Project Overview
Fast Facts
- CLIENTSingleton Council
- LOCATIONHerbert Street Bridge, Christian Badior Bridge & Maryvale Bridge, NSW
- YEAR OF COMPLETION2025
Scope of Works
- Solution for abutment repair works with quality standards.
- Scour protection works with proper drainage provisions.
- Construction of walls below the abutment and approaches.
- Placement of concrete to fill the voids to avoid water seepage and penetration.
- Placement of semi perforated pipes and geotextile fabrics at every stage of works.
- Spray seal works on abutment approaches.
Challenges and Outcomes
- Remote site location presenting logistical and access constraints.
- Limited access to other end of the bridge.
- Limited availability of skilled labour and materials within the region.
- Adverse weather and flood events affecting scheduling and site accessibility.
- Challenging ground conditions requiring adaptive and innovative foundation solutions.
Despite these challenges, Fortec successfully delivered the 3 Bridge Abutment Repair project to a high standard of safety, quality, and performance, achieving all project milestones and exceeding client expectations.