Fortec was engaged by Main Road Western Australia to undertake works on three bridges across the Wheatbelt, with a further four awarded as Variations.
The works included Replacement of Structure 4046 with an RCP Culvert in Calingiri; major timber and concrete repair works to Structure 4031 in Chittering and Structure 4399 in Northam; and as a variation some surfacing and concrete repairs to Bridge 0020A in Williams; pier replacements on Bridge 0410 in Quindanning (Williams) and temporary propping works and other miscellaneous repairs to Bridges 0412 and 0414 in Williams.